Timeline


Jan. 2022

May 2021

May 2022

Rooms Constructed

Order Confirmed

Final Handover

Before Construction

During Construction

After Construction

Project Highlights

  • Plant was converted from an IBM manufacturing facility.

  • Integrated existing structural steel and chilled water system for efficient in-room sensible cooling.

  • Created a hybrid of pre-engineered components and custom spaces that enabled precise design submittals in just 6 weeks.

  • Airtho’s flexible project management was able to adapt and execute on a tight schedule with rapid updates to technical needs and a tight budget of a fast-growing start-up company.