Case Study

R&D Facility Dry Room

Location: Montreal, Canada

Size: 1,875 ft²

Download Case Study

Timeline


June 2021

Dec. 2021

Jan. 2022

Rooms Constructed

Order Confirmed

Final Handover

Project Highlights

    • Locating the DHU directly on top of the room created an efficient ductwork design.

    • Paired with high-efficiency terminal HEPA filters, the design created a system with 2.5” total external static pressure.

    • Full submittal package in 2 weeks.

    • Delivery of room components within 3 months from PO.

    • Super Steel™ supported the critical loads of Airtho’s dry room package without any required upgrades to the building.

    • Located in a mixed-use facility, Airtho aligned access to the walkable plenum cap directly from the existing second floor offices for ease of access.